View TRAK:EVp-03 Capability Phasing Viewpoint
Title
EVp-03 - Capability Phasing Viewpoint
Version
6
Date
8th March 2011
Overview
The EVp-03 - Capability Phasing Viewpoint is part of the Enterprise Perspective and one of the 21 TRAK Architecture Viewpoints.
The EVp-03 Capability Phasing Viewpoint provides a way of describing the duration and phasing of capabilities.
It is the specification for the TRAK::EV-03 Capability Phasing architecture view.
Stakeholders Addressed
- Builder of Enterprise
- Developer of Enterprise
- Maintainer of Enterprise
- Owner of Enterprise
- Acquirer of System
- Disposer of System
Concerns Addressed
When is capability required?
Is this capability realised by any solutions?
Are there any capability gaps?
![]()
Full size:File:evp03StakeholderConcern.gif
Covered by TRAK IPR and licenses
Description
Describes when Capabilities (planned or actual) are fielded over time. Capabilities are enduring since on their own they have no associated time. An Enterprise has a start and finish date and therefore when a capability is tied to an enterprise this defines a period for which that capability is required. Similarly a system can realise a capability and when delivered or removed by a project activity there is a time period during which the required capability is realised.
The EVp-03 can be used to show the capabilities needed, the capabilities realised (via the solution and procurement perspectives) or contrast the two to determine Capability gaps. The EVp-03 also describes dependencies between capabilities.
Covered by TRAK IPR and licenses
The phasing of capability requires a duration - start and finish times to be defined. This is available from 2 sources:
- Enterprise attributes. In this case the phasing shown is the required Capability phasing.
- Project Activity attributes in conjunction with the Project Activity delivers / removes System. This is shown on the PrVp-02 Procurement Timeline Architecture Viewpoint which describes how capability is provided or removed by virtue of a system. The net realised capability can only therefore be described if the PrVp-02 is present.
Comparing the required capability phasing with the realised capability phasing provides a way to describe capability gaps.
Mandatory Metamodel Tuples
Capabilities Needed
- Enterprise requires Capability
Capabilities Realised
- Project Activity delivers System
- Project Activity removes System
- System realises Capability
Covered by TRAK IPR and licenses
Optional Metamodel Tuples
Universal
- Concern about Architecture Description Element
- Architecture Description Element traces to Document
- Standard governs Architecture Description Element
- Architecture Description Element traces to Requirement
If any of these optional metamodel elements are added then the appropriate TRAK Master Architecture View must be provided.
Covered by TRAK IPR and licenses
Well-Formedness
An EV-03 view shall contain:
[capabilities needed - phasing]
- at least one Enterprise (the subject of the view)
- every Enterprise must have at least one Capability
- the Enterprise must have both a start and a finish date. If it doesn’t it is assumed to be enduring (exists at all dates)
- the time period during which a Capability is required must be visible (as the point is to show change / dependency with time).
[capabilities realised]
In addition if the capabilities realised are to be shown:
- at least one System
- every System must realise at least one of the Capabilities from the [capabilities needed]
- every System must be associated with 2 Project Activities (one to introduce the System into service, the other to remove it from service)
- every Project Activity must have both a start and a finish date
Covered by TRAK IPR and licenses
The properties/attributes for elements are defined within the TRAK Metamodel document.
Presentation
- table or matrix ([capabilities needed] Capability vs time taken from start and finish dates for each Enterprise; i.e. Capability vs Enterprise [capabilities realised] Capability vs time taken from start and finish dates for each Project Activity that delivers/removes the Capability - i.e. Capability vs System; or contrast the two). The important feature is to be able to see how capability changes with time.
- block diagram (connected blocks to represent Enterprise, Capability, Project Activity and System)
table form:
EV-03 Table or Matrix Form Capability Required by Enterprise Start Date Finish Date Depends on Capability Ca1 E01 T1 T5 - Ca2 E01 T1 T5 Ca3 Ca3 E02 T0 T4 -
Capabilities needed: - hierarchy (enduring / no time specified):
Phasing:
Covered by TRAK IPR and licenses
Examples
Views Needed to Construct
- EV-02 - master architecture view for Capability
- PrV-02 - master architecture view for Project Activity
- SV-01 (if System realises Capability shown) - master architecture view for Resource (System)
Consistency Rules
Covered by TRAK IPR and licenses
Further rules are applied through the TRAK Bye Laws
Configuration History
The TRAK Viewpoints project on Sourceforge (trakviewpoints.sourceforge.net) maintains a version-controlled repository. The change record is at http://trakviewpoints.svn.sourceforge.net/viewvc/trakviewpoints/trunk/?view=log
Comments
Other Frameworks
See:
- DODAF::CV-3 Capability Phasing Model
- MODAF::StV-3 Capability Phasing View
- NAF::NCV-3 Capability Phasing Subview
There is no equivalent in DNDAF to the TRAK Enterprise Perspective - see Architecture Framework Comparison.
References
- TRAK Enterprise Architecture Framework Viewpoints. http://trakviewpoints.sourceforge.net
Category:Framework -> Viewpoint
Category:Framework -> Specification
Category:Enterprise
Category:Strategic
Clip to Evernote